1.
INTRODUCTION
& GENERAL INFORMATION
|
This
method of statement is made because on
location of Topslab OH 54 there is a footmark. This method of statement
provides the details of materials, equipment and sequence of work related to repairing
Top Slab OH 54 .
2.
MATERIAL
|
Required
material for concreting work ie :
a. SikaGrout
212
3.
EQUIPMENTS
AND TOOLS
|
Required
material for concreting work ie:
a. Small
Equipment for Chiping Concrete
b. Hammer
c. Crane
& Bucket
4.
EXECUTION
METHOD
|
The concreting work will be proceed as the follow (see
attachment) :
a. Preparation
of small equipment.
b. Chiping
the footmark area of Top Slab OH 54 Sec
8.1
c. The
surface must be clean before concreting
d. Apply
a bonding coat of 1part RHEOMIX® 121 diluted with 2 parts water
e. Concreting
of Footmark area using SikaGrout 212
f. Screed
the surface of concrete.
5.
ATTACHMENT
|
Attachment
2 :
Catalog SikaGrout 212.
Attachment
3 :
Catalog BASF Rheomix 121
Reparation Method
Catalog
SIKAGROUT 212
SCELLEMENT
Catalog BASF RHEOMIX 121